How to build an 8'x10' Storage Shed

Author: Les Kenny
Recommend  
Page Contents
1: Introduction - disclaimer
2: About the measurements
3: Materials list
4: Plans - floor, roof and stud layout
5: Plans - front elevation and roof section
6: The floor and wall frames
7: Standing the frames and the roof beam
8:   The roof frame and the sheathing
9:   The roof trim and roof cover  you are on this page
10: The vertical boards and battens
11: Making the door
12: Installing the door
13: Nailing and fastening information
14: Glossary of terms
bullet User Photos/Comments

Note: This complete project (all the pages together in one handy pdf file,ad free) can be purchased online and downloaded immediately to your computer for only $5.  Grab here.

To view all available plans in downloadable pdf file click here.

10. Fascia, Rake Board and Builders Felt

Nail the rake boards to the ends of the purlins along each gable rake and make flush with the top of the purlins.
Join the rake boards at the apex (vertical cut) and cut the other end vertically, 175mm (6") past the ends of the rafters.

Cut and fix the fascia board to the ends of the rafters, between the rake boards.
Make the top edge of the fascia board flush with the top of the purlin.

Cover the roof with builders felt prior to the corrugated roofing iron going on.

11. The Roof

Fix the roofing iron to the purlins with appropriate roofing nails/screws.

Fix to the top and bottom purlins at every second corrugation and fix to the intermediate purlins at every 3rd or 4th corrugation.

Fix through the high side of the corrugation.
Overhang the roofing approx 65mm (2 1/2") past the Fascia Board.

12. The Ridge Capping and Rake Flashing

Standard ridge capping is about 130 (5") each side of the apex, but can vary and any size can be made to order.
Have the ridge flashing in mind when positioning the top Purlin.

Fix the ridge capping to the Purlin at every second corrugation.
The rake flashing goes under the ridge capping at the top.
Fix to each purlin (through two corrugations) and also to the side of the rake board.

the Fascia, Rake Board and Builders Felt fixed to the shed roof
The shed roof
The Ridge Capping and Rake Flashing fixed to the shed