How to build a Kids Play Cottage
Page Contents
1: Introduction, measurements, wood sizes
2: Material requirements
3: Plans - walls and panels
4: Plans - floor and door
5: Cutting the panels, making the floor
6: Making the walls
7: Adding battens, window/door openings

8:  Levelling the floor, standing the walls
9:  Making the roof  you are on this page
10: Fitting the ridge capping
11: Fitting the valley boards
12: Making the door
13: Fitting the door
bullet User Photos/Comments

Note: This complete project (all the pages together in one handy pdf file,ad free) can be purchased online and downloaded immediately to your computer for only $5.  Grab here.

To view all available plans in downloadable pdf file click here.

Step 12. Making the roof beams making and fitting the playhouse roof beams

For the roof beam...
cut two pieces of 100mm x 25mm (1" x 4") stock the same length as the floor, which should be 1590mm (63 5/8") long.
Rip down (cut lengthwise) each piece so that one side is 25mm (1") wider than the other side, thus being able to make a symmetrical inverted 'V' when the two pieces are nailed together at right-angles. Confused? take a careful look at the diagram below.

playhouse roof beams

Next cut one of the beams in half and then cut back at an angle of 45 degrees. (Also see diagram.)
Then fix a metal strap (or similar fastener) to the square-cut end of each beam (4 in all).
Run (overhang) the metal straps by 35mm (1 3/8") past each beam.

Step 13. Fixing the roof beams in place

Sit the long beam in position at the apex between the two side walls. The metal strap overhang will stop the beam from falling while it is being nailed in place.

Next, fix the half beams in place in the same manner between the apex of the front and rear walls and the middle of the long beam.

Step 14. Fixing the roof panels in place

First nail the top of the roof panels flush (even) with the top of the beam.
When the tops of all roof panels are fixed securely to the roof beam, THEN nail the panels to the raking (top) wall battens.